#acl CirrusUserGroup:read,write,delete,revert | #acl CirrusUserGroup:read,write,delete,revert All:read That page is planned to use for a diary of the CIRRUS-III Project. It's opened to view from everywhere. (If you like to contribute add a date entry by {{{@ DATE @}}} without the blanks and some usefull comments) ----- ##[[Date(2006-11-17T12:56:10Z)]] Start of this page === Tu., 28.November 2006 === preparations for the double flight started at 5:00 in the morning probably we will stop at Kiruna airport take off is planned for 9:22 local time may be we can reach stratospheric air take off at 9:22 === Mo., 27. November 2006 === Third flight take off 11:42 local time attachment:thumbnail_100_2196.jpg === Fr., 24. November 2006 === Second flight take off planned for 11:30 local time /!\ Probably science meeting in the evening /!\ === Do., 23. November 2006 === /!\ First Flight 11:30 Local Time /!\ Take off was at 12:40 Local Time! ;-) === Mi., 22. November 2006 === /!\ Meeting 15:30 Uhr /!\ Die Integration soll bis heute Abend abgeschlossen sein. Morgen früh dann tanken und EMC Test vor dem Flug. === Di., 21. November 2006 === /!\ Meeting 10:30 Uhr /!\ Die Integration soll bis heute Abend abgeschlossen sein. Morgen früh dann wiegen des Flugzeugs und EMC Test. Mittags Gerätetests im Flugzeug. Erster Flug geplant für Donnerstag, 23. 11. 2006, gegen Mittag. Laut Vorhersage haben wir dann optimale Bedingungen, d.h wir können zuerst durch den Conveyor Belt des Tiefs 'Kira' fliegen und dann ausgiebig den zugehörigen Frontcirrus beproben. Haltet alle die Daumen dass das so bleibt! === Mo., 20. November 2006 === Integration der wingpod Instrumente für den Abend geplant === So., 19. November 2006 === weitere Teilnehmer sind eingetroffen Reimar === Sa., 18. November 2006 === Die ersten Kampagnenteilnehmer sind ohne weitere Pannen gut in Hohn angekommen. Aalversuper wie immer ... :-) Martina |
That page is planned to use for a diary of the CIRRUS-III Project. It's opened to view from everywhere.
(If you like to contribute add a date entry by @ DATE @ without the blanks and some usefull comments)
Tu., 28.November 2006
preparations for the double flight started at 5:00 in the morning
probably we will stop at Kiruna airport
take off is planned for 9:22 local time
may be we can reach stratospheric air
take off at 9:22
Mo., 27. November 2006
Third flight take off 11:42 local time
attachment:thumbnail_100_2196.jpg
Fr., 24. November 2006
Second flight take off planned for 11:30 local time
Probably science meeting in the evening
Do., 23. November 2006
First Flight 11:30 Local Time
Take off was at 12:40 Local Time!
Mi., 22. November 2006
Meeting 15:30 Uhr
Die Integration soll bis heute Abend abgeschlossen sein. Morgen früh dann tanken und EMC Test vor dem Flug.
Di., 21. November 2006
Meeting 10:30 Uhr
Die Integration soll bis heute Abend abgeschlossen sein. Morgen früh dann wiegen des Flugzeugs und EMC Test. Mittags Gerätetests im Flugzeug.
Erster Flug geplant für Donnerstag, 23. 11. 2006, gegen Mittag.
Laut Vorhersage haben wir dann optimale Bedingungen, d.h wir können zuerst durch den Conveyor Belt des Tiefs 'Kira' fliegen und dann ausgiebig den zugehörigen Frontcirrus beproben. Haltet alle die Daumen dass das so bleibt!
Mo., 20. November 2006
Integration der wingpod Instrumente für den Abend geplant
So., 19. November 2006
weitere Teilnehmer sind eingetroffen
Reimar
Sa., 18. November 2006
Die ersten Kampagnenteilnehmer sind ohne weitere Pannen gut in Hohn angekommen. Aalversuper wie immer ...